India's first double-decker flyover opens in Mumbai

Mumbai: India's first double-decker flyover was opened for public use in this west coast megapolis and the country's commercial capital Friday.

 The project - Santacruz-Chembur Link Road (SCLR) - will provide a critical east-west suburban link in the city and has slashed travel time from the earlier 90 minutes to barely 20 minutes now, entailing huge savings in time and fuel costs for commuters.

The long delay resulted in huge cost overruns - from the original estimated Rs.1.15 billion to Rs.4.54 billion at completion stage.

The third and final phase of elections are due here April 24.

The World Bank-funded SCLR gives not only the crucial east-west link within the city, but also provides a faster access for onward destinations like Pune, Goa and Nashik from the state, an official said.

Mumbai Metropolitan Region Development Authority (MMRDA) officials attributed the delays mainly to the rehabilitation of around 3,500 families residing on the route of the flyover at Gazi Nagar, Buddha Colony, Indira Colony, Rahul Nagar and other slum pockets.

Significant time was also lost in securing permission by the Indian Railways to construct the double-decker part of the flyover, the officials pointed out.

Besides the SCLR, Mumbaikars have been given a whole lot of mega infrastructure goodies in the past few weeks, including the swank, world-class four-decker Terminal II at the Chhatrapati Shivaji International Airport, the Eastern Freeway Project with two long tunnels - the first ever in an urban set-up in the country.

There is also the new Sahar Elevated Access Road, including a flyover and subway outside Mumbai Airport, the sea-plane services, India's tallest ATC tower, besides several other smaller projects in and around the country's commercial capital.